Iraqi public tenders in brief

Since February 2026, federal public procurement in Iraq has followed new rules. The Ministry of Planning's Instructions No. 1 of 2025 for Implementing Public Contracts were published in the Official Gazette on 17 November 2025 and entered into force 90 days later. They replaced the 2014 instructions; contracts signed under the old rules remain subject to them.

Who do they apply to?

Federal institutions, governorates and state-owned companies. Contracts financed by international donors generally follow the funder's own rules, and defence and security procurement has its own rules.

Types of procedure

The default is the public tender. There are also limited tenders (with at least two pre-qualified bidders), two-stage tenders, direct invitations (to at least three companies, in specified cases), single-bid procedures (with the central committee's approval), design competitions and framework agreements.

Where are tenders published?

On the unified electronic platform and in two national newspapers; international tenders are also sent through the commercial attachés of Iraqi embassies. The bidding period is 10–60 days. Tender documents must be purchased, and the payment receipt must be attached to the bid. Use of the Ministry of Planning's standard bidding documents is mandatory.

Guarantees

  • Bid security: 1–3% of the estimated cost as a fixed amount; the higher the estimated cost, the lower the percentage. It can be provided as a bank guarantee, a certified cheque or, up to a set amount, in cash. Under the standard documents it must remain valid for 28 days beyond the bid validity period. A suitable bid security is a condition of a valid bid.
  • Performance guarantee: 5% of the contract value, in the contract currency, after the award notice and before signing. It is released after final acceptance.

Evaluation and award

Bids are opened in public and then evaluated confidentially. Bids within a 20% band around the estimated cost take part in the evaluation. The award is ratified by the central award ratification committee. The contract must be signed within 30 days, or within 45 days if a foreign winner still has to register a branch. Bidders may file objections within 7 working days.

What a complete bid contains

Under the rules, a complete bid has:

  • a valid bid security of the right amount;
  • the tax clearance letter;
  • legalised documents throughout;
  • the receipt for the purchased tender documents, with the documents unaltered;
  • its own management, since the same manager or partner may appear in only one bid;
  • a certified consortium agreement;
  • a price within the 20% band around the estimated cost.

In the Kurdistan Region

The Region also has its own procurement rules, with its own standard documents. There, always follow the rules referred to in the specific tender notice.

ICC helps align bid documentation, legalise documents and coordinate between the parties.

Sources: mop.gov.iq – Instructions No. 1 of 2025 for Implementing Public Contracts (Official Gazette No. 4849) · mop.gov.iq – standard bidding documents · mop.gov.iq – General Government Contracts Department

This article is general information, not legal advice. Rules may change; always check the specific tender notice and current legislation before making decisions.